On-going works;

  • Concrete works have been completed to badger road and red barriers will be removed next week
  • Our site boundary is to be moved out towards the centre of badger road, where we will be digging more of site, where the entrances will be formed
  • Currently the big hole in the ground is for a water tank, which will be backfilled w.c.11/4/22
  • On-site cladding is being installed to the roof and walls
  • Ground works are being undertaken for drainage over the coming weeks to the front yard